This webpage has been provided in order to offer a quick and easy reference source for viewing the planning exhibits that will explain the LOCATIONS of the featured mechanical elements, and how the PROPOSED development is being considered.

 

9-21-23 DISCUSSION POINTS

Plan REV #5 of the preliminary layout information below will address the markup corrections recently requested;
 
1.) Equipment Selections (DETERMINED UPON ACCEPTANCE OF PRELIMINARY LAYOUT)
2.) Pipe Sizes (SEE BELOW)
3.) Plumbing / Pipe Layout (DETERMINED UPON ACCEPTANCE OF PRELIMINARY LAYOUT)
4.) Drain Sizes (SEE PRELIMINARY PLAN BELOW)
5.) Material Selections for all pool embeds, inserts, penetrations (DETERMINED UPON ACCEPTANCE OF PRELIMINARY LAYOUT)
6.) Lead time on materials. (OUTSIDE MECHANICAL DESIGN WORK SCOPE)
7.) Review Equipment room size, power, water, drain requirements (PER REV #5)
8.) Data requirements (TO BE DISCUSSED)
9.) Power requirements (100-A, SINGLE PHASE, 120/240v)
10.) Water requirements (15-GPM / 40-PSI AS WPOC – BACK-FLOW PREVENTION UNIT)
11.) Sewage requirements (4.00″ CONNECTED TO BACKWASH SUMP – SUMP = 4′-W x 4′-L x 3′-D = 48-CU.FT. = 360-USG)
12.) Deck Drainage requirements (BY OTHERS)

 

PRELIMINARY SWIMMING POOL LAYOUT 9-20-23 – REV-#5

 

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

 

PRELIMINARY SWIMMING POOL LAYOUT 9-20-23 - REV #5

 

SWIMMING POOL LAYOUT REV #5
The Swimming Pool Layout is diagrammatically shown. This drawing provides a series of assigned “Details”, which will offer further explanation for the code compliant intended installation instruction specifics.
 
Each of the numbered assignments refers to a featured component and the drawing exhibits the intended locations for each. Some of the components exhibited are not in the Design Work Scope of the swimming pool mechanical design but are indicated so that other Design Professionals can familiarize themselves with what will be necessary in order to collaborate a code compliant swimming pool plan for submission.
 
In summery here are the assigned item numbers that have not been made inclusive to the swimming pool mechanical Design Work Scope;

     

  • ITEM #12 GAS SUPPLY
  • ITEM #13 GAS SLEEVING
  • ITEM #14 WATER SUPPLY
  • ITEM #17 HOSE BIBBS
  • ITEM #18 SUB-PANELS
  • ITEM #21 EQUIPMENT ENCLOSURE
  • ITEM #37 911 – EMERGENCY TELEPHONE
  • ITEM #57 DRESSING ROOM
  • ITEM #58 SHOWERS
  • ITEM #59 TOILETS
  • ITEM #60 LAVATORY
  • ITEM #61 FINISH FLOOR
  • ITEM #62 INTERIOR SURFACES
  • ITEM #63 PRIVACY
  • ITEM #64 DRINKING FOUNTAIN
  • ITEM #65 SELF CLOSING DOORS & GATES
  • ITEM #66 SAFETY BARRIER – FENCING
  • ITEM #67 STRUCTURAL ENGINEERING

PRELIMINARY EQUIPMENT PAD LAYOUT 9-20-23 – REV-#5

The preliminary Equipment Pad indicates the dimensional space being allocated by the Architect for the Swimming Pool Equipment Room. The purpose of which is to allow a collaboration with the other project Design Professionals so that we can all accomadate the supply of the utility infrastructures to the Equipment Room location together with evaluating their sizes / capacities i.e.; Electric Power = Amperes, Gas = Type and Pipe Size, etc..(If a Gas Heater is applicable).
 
NOTE: Please confirm that the Pool Heat Pump’s locations are finalized

 

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

 

PRELIMINARY EQUIPMENT PAD LAYOUT 9-20-23 - REV-#5

 

NOTE: ADDITIONAL SPACE HAS BEEN ALLOCATED FOR THE STORAGE OF CHEMICALS (ORP / pH) AND A DUAL HEAT PUMP SYSTEM, SEE DIMENSIONS

 

PRELIMINARY POOL SECTION LAYOUT 9-20-23 – REV-#5

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

 

POOL SECTION 9-20-23 - REV-#5

 

POOL PLUMBING LAYOUT

NOTE #1: There are six (6) Wall Returns, six (6) Floor Returns, four (4) Surface Skimmers, one (1) Main Drain, and six (6) 12v/ 190w LED Lights.

 

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

PRELIMINARY EQUIPMENT PAD LAYOUT 7-25-23

 

PIPING SYSTEM, PIPE SIZING

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

PIPING SYSTEM, PIPE SIZING

 

POOL VOLUME CALCULATIONS

NOTE #2: The pool’s water volume and turnover rate has been calculated based upon 26,161-Gals. This relates to a 72.67-GPM Design turnover rate. The system design has a capability of providing an additional 33.33-GPM rate of flow when programed to due so, see calculations below;

 

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

POOL VOLUME CALCULATIONS

 

NOTE #2: There is NOT an ADA Lift Chair but, one can be added if desired.

 

NOTE #3: The pool’s surrounding decking area and coping will need to be defined on the architectural drawings and the deck lighting will need to be shown on the electrical drawings. Therefore the deck lighting requirement will be .50w/SF of illumination. Please provide this information to the Electrical Engineer together with the anticipated load values for all equipment, upon final determination.
 

NOTE #4: I have assumed that there will be decking around the entire pool and therefore I have indicted a “Slotted Drain” for all of the area adjacent to the pool deck. Therefore the decking surface is to be sloped away from the Building’s foundation and away from the edge of the pool and intersect at an inverted elevation TBD lower than the starting elevation at each edge. This will allow water to migrate toward the center and be carried out via a 4.00″ pipe to be installed below the deck. The deck’s slope is equal to 1/4″ per foot fall toward the center. If something differs from this approach please markup the preliminary plan showing me the limits of the intended deck that would be reflecting otherwise.

 

EXAMPLES OF DETAIL ASSIGNMENTS

Click on image below to enlarge view, use your Browser’s back-arrow key to return to this page

 

SURFACE SKIMMER

#1 SURFACE SKIMMER

 

PIPE PENETRATIONS – NO LEAK FLANGES

PIPE PENETRATIONS - NO LEAK FLANGES

 

PIPE & CONDUIT EMBEDDED PLAN NOTES

PIPE & CONDUIT EMBEDDED PLAN NOTES width=

 

MAIN DRAIN SECTION – 32″ CHANNEL

MAIN DRAIN SECTION - 32

 

INSTRUCTIONS

Please review the information and provide directions for any desired changes. One (1) revision has been made inclusive in our original Design Fee Schedule. Additional revisions beyond the one (1) made inclusive are considered billable work.